Zenit arena location. Zenit Arena stadium (43 photos). year - Almost ready

From 1950 to 2006 in St. Petersburg on Krestovsky Island there was a stadium named after. Kirov. It was one of the largest stadiums in the world - it was the largest in the entire Soviet Union, Russia and Europe.

The last official match on that field was played on July 6, 2006, and by the end of 2006 the stadium was dismantled in order to begin construction of a new and almost the most expensive stadium in the world on the same site. The project budget is approximately 35 billion rubles.

And construction began...

During 2007, the pile field was completed and the earthworks were completely completed. In 2008, the project was ready, it passed the state examination, but due to various conflicts, construction was stopped.

In December 2008, construction work was resumed. But already in December 2009, after checking the stadium project for compliance with FIFA requirements, it became clear that, according to a number of criteria, the stadium already under construction did not meet these standards. The main complaints were made about the configuration of the stands (ensuring comfortable visibility, the location of hatches) and the layout of the sub-tribune rooms, which were divided by thick walls into small compartments. There were practically no halls or open spaces inside. To correct the identified deficiencies, in April 2010, a new general designer was brought in - Mosproekt-4, which has extensive experience in designing sports facilities (for example, the Lokomotiv stadium in Moscow).

The layout of the premises under the stands and the configuration of the stands were brought in accordance with the FIFA requirements for stadiums of this level. Large halls and free spaces appeared, and places were found to accommodate additional cafes and bars at all levels of the stadium. Due to the changes being made, construction was stopped again in December 2009 and resumed in full in August 2010.

Since 2008, construction has been carried out by Inzhtransstroy, part of the Transstroy structure.

The new stadium will host World Cup matches in 2018. Including the semi-finals. The final match will take place in Luzhniki. It is planned that by the time construction is completed, the stadium will become one of the most technologically advanced and sophisticated sports facilities in Europe. There will be no athletics tracks on it and it will be intended only for football matches.

Let's take a look at this engineering marvel. I will reveal several technical solutions that are worth focusing on:
- roll-out football field;
- a huge reinforced concrete bridge with a span of 100 meters on which the stand is located;
- sliding roof.

And stopping construction was only beneficial. During this time, the pile field has stabilized and now it no longer produces sediment. There is another story connected with him. The fact is that the first general contractor (Avant) overdid it a little with the piles, and there were more of them than necessary. As a result, the bearing capacity of the field turned out to be twice as large as planned according to the project. In general, a dark story happened with them... But then, when the project was changed, it played into the hands - the new stadium project and all the changes fit perfectly into the limits of weights and loads. It was only necessary to strengthen the grillages under the stadium bowl.

Well, enough introductions, it's time to watch!

Beautiful view from the Primorsky district. The stadium itself resembles a flying saucer. By the way, it has a specially aerodynamic shape, since wind loads especially had to be taken into account here.

St. Petersburg can be called one of the most beautiful cities in Russia and it would not be surprising if everyone had the opportunity to see it from all sides. There would be no doubt about what was said. You can study the city from the inside for many months, examining its quaint streets, the architecture of local buildings, attractions and other objects that attract tourists, but a truly fascinating sight opens up on St. Petersburg from a bird's eye view. Today you can see several districts of the city from the screen of your own computer, through web cameras installed on its territory. This broadcast provides a panorama of the city near the Krestovsky stadium. There is no other way you will be able to personally see what this building looks like from the outside, to appreciate the scale of the architect’s idea, the beauty of the structure. The camera is installed so high that it can cover several hundred kilometers of the city in all directions from the stadium. The frame includes a water surface, a road chain, an undeveloped area and the stadium itself. If you look closely, it becomes clear how carefully everything was thought out, the area around the stadium is delimited into squares, there are several access roads so as not to create traffic jams and large parking lots. Of course, from such a height it will not be possible to examine the stadium and other objects in great detail, but that was not the main goal. The webcam works around the clock, any network user has access to it, regardless of their geographic location. The device works online, there are no problems with broadcasting if the connection to the network is good.

The new home arena of the Zenit football club will be built on the site of the S. M. Kirov stadium, located in the western part of Krestovsky Island.

From November 15, 2005 to August 23, 2006, on the initiative of the government of St. Petersburg, a competition was held for the best project for a new stadium. The expert commission gave preference to the “Spaceship” project by Japanese architect Kisho Kurokawa.

The customer for the construction of the new stadium is the St. Petersburg Construction Committee. The general designer of the project is Kisho Kurokawa architects & associates. The general construction contractor is ZAO Engineering Corporation Transstroy.

The new project provides that 68 thousand spectators will be able to be in the arena at a time. The height of the seven-story building will be 56.6 meters, the area of ​​the football field will be 9840 square meters. The arena will be covered with a retractable roof, which will allow matches to be held in comfortable conditions (operating temperature - +15) in the winter season.

Big projects always arouse equally great interest. Many, without really understanding it, begin to scold them. It's the easiest thing! Others, turning their heads a little, admire the engineering and technical solutions. The Zenit Arena stadium under construction in St. Petersburg did not escape this fate. The project is complex, expensive, but incredibly interesting from a technical standpoint. And some of the solutions used at the stadium are simply unique.

I had the opportunity to spend one day at a construction site and was repeatedly surprised by many interesting moments. But first, a little history.

From 1950 to 2006 in St. Petersburg on Krestovsky Island there was a stadium named after. Kirov. It was one of the largest stadiums in the world - it was the largest in the entire Soviet Union, Russia and Europe.

The last official match on that field was played on July 6, 2006, and by the end of 2006 the stadium was dismantled in order to begin construction of a new and almost the most expensive stadium in the world on the same site. The project budget is approximately 35 billion rubles.

And construction began...

During 2007, the pile field was completed and the earthworks were completely completed. In 2008, the project was ready, it passed the state examination, but due to various conflicts, construction was stopped.

In December 2008, construction work was resumed. But already in December 2009, after checking the stadium project for compliance with FIFA requirements, it became clear that, according to a number of criteria, the stadium already under construction did not meet these standards. The main complaints were made about the configuration of the stands (ensuring comfortable visibility, the location of hatches) and the layout of the sub-tribune rooms, which were divided by thick walls into small compartments. There were practically no halls or open spaces inside. To correct the identified deficiencies, in April 2010, a new general designer was brought in - Mosproekt-4, which has extensive experience in designing sports facilities (for example, the Lokomotiv stadium in Moscow).

The layout of the premises under the stands and the configuration of the stands were brought in accordance with the FIFA requirements for stadiums of this level. Large halls and free spaces appeared, and places were found to accommodate additional cafes and bars at all levels of the stadium. Due to the changes being made, construction was stopped again in December 2009 and resumed in full in August 2010.

Since 2008, construction has been carried out by Inzhtransstroy, part of the Transstroy structure.

The new stadium will host World Cup matches in 2018. Including the semi-finals. The final match will take place in Luzhniki. It is planned that by the time construction is completed, the stadium will become one of the most technologically advanced and sophisticated sports facilities in Europe. There will be no athletics tracks on it and it will be intended only for football matches.

Let's take a look at this engineering marvel. I will reveal several technical solutions that are worth focusing on:
- roll-out football field;
- a huge reinforced concrete bridge with a span of 100 meters on which the stand is located;
- sliding roof.

And stopping construction was only beneficial. During this time, the pile field has stabilized and now it no longer produces sediment. There is another story connected with him. The fact is that the first general contractor (Avant) overdid it a little with the piles, and there were more of them than necessary. As a result, the bearing capacity of the field turned out to be twice as large as planned according to the project. In general, a dark story happened with them... But then, when the project was changed, it played into the hands - the new stadium project and all the changes fit perfectly into the limits of weights and loads. It was only necessary to strengthen the grillages under the stadium bowl.

Well, enough introductions, it's time to watch!


1. Beautiful view from the Primorsky district. The stadium itself resembles a flying saucer. By the way, it has a specially aerodynamic shape, since wind loads especially had to be taken into account here.

2. The stadium will host all the main cultural events and concerts of St. Petersburg. And imagine some rock concert at this stadium...


3. The negative angle of the facade, although beautiful, imposes special standards for design and calculations. Also, nothing should fall off from this façade in the event of a fire to ensure the evacuation of spectators. In general, the closest attention is paid to fire regulations and safety at the stadium.


4. In terms of area, this is the largest stadium in Eastern Europe.


5. Due to the fact that weather conditions in St. Petersburg are unfavorable for grass growth in winter, and the city is the northernmost of the Premier League, the authors of the project made an architectural decision in which the stadium field will extend beyond its boundaries, and the roof will be retractable to cover the field during bad weather and the cold season. The field itself will live outside, blown by the sea wind. In cold weather it will be in the greenhouse. But most importantly, the natural lawn will receive the necessary sunlight to grow. And inside the stadium, without a football field, you can hold concerts, exhibitions and other public events without fear of damaging the lawn.


6. The original design of the stadium was made of German steel. But then they decided to save money and make everything from reinforced concrete. But we were faced with the fact that the stadium structures, when using concrete, became much thicker and the architectural design did not fit into the existing structure. We had to do exorbitant reinforcement of the structures, but it still turned out cheaper than using imported steel. Now the stadium bowl is completely ready, and the metal roof structure is one third complete.


7. An unusual method was used to install 22,000 tons of metal roof structures. Usually temporary support structures are created and installation is carried out on them. But this method does not provide the necessary accuracy and, most importantly, it requires two 700-ton cranes. But they didn’t want to fit in the stadium.


8. Therefore, we decided to mount all the roof segments on a slipway using tower cranes in one place, and then move them along guide rails to the design position. This method is more complicated and requires more temporary structures, but ultimately provides the highest assembly accuracy and time savings.


9. While it’s difficult to see what will happen in the clutter of building structures, the renderings allow it.


10. Stadium in football configuration.


11. The decision was very controversial and it met with many opponents. But the installation of the roof that began showed that this was the right path.


12. Each column of the temporary structure has a unique design and mounting in the bowl. Some columns are placed directly on the stands, but most pierce them to the required level.


13. The highlight of the stadium is the bridge that allows the field to be rolled out onto the street. The span of the flat floor is more than 100 meters! This is a unique prestressed concrete structure. The maximum standard deflection of the bottom slab of the bridge along its central axis (in the middle of the span) is 210 mm, and the design deflection is 87 mm. On this bridge there is a stand with a fan section (this means jumping and other football joys) and part of the roof. Essentially, it's like a piece of pie that is cut off from the rest of the structure and lives its own life.


14. There will be no bars, restaurants or other premises inside the stands in this sector. Only rigid diaphragms and small rooms.


15. Now the bridge is completely ready. No, it's actually surprising. It would be nice if it were a vault, I still understand. But a flat ceiling with such tolerances... Fantastic.


16. And this is the design of a football field. Its weight is about 7.8 thousand tons. Initially it was assumed that the structure would be pushed under the stadium by hydraulics, but this was slow, difficult and unreliable. As a result, this part was also redesigned - the entire football field will be slightly raised on an air cushion, relieving part of the load on the rollers. And then electric motors move the field for several hours. Unlike half a day in the case of hydraulic pushers.


17. On the northern stand there is a slipway where the roof segments are assembled.


18. Another feature of the stadium will be a single control center. All information about the stadium, the movement of people, traffic congestion on highways, etc. will flow here.


19. A video surveillance system will be installed at the stadium, which in real time allows you to track any spectator from the entrance security cordons to his place in the stands. The system immediately identifies his ticket, his portrait and his track record as a fan.


20. There will be a smoke removal and fire extinguishing system under the roof. All this is also, of course, unique. In the case of a fire extinguishing system, it can act very locally. If someone carried a fire (suddenly) and lit it, then the system recognizes the place (accordingly, we calculate who it is), a water cloud is created around the place from sprayers, and water is supplied from above from a firefighter to this particular person. Complete space, in short.


21. A reconstructed fountain that was near the Kirov stadium.


22. But, it’s time to go up to the slipway. See the slanted gray thing? This is the pylon on which the roof will rest, in addition to the walls. The truss under the pylon is a temporary structure for the period of roof installation.


23. Primorsky district.


24. The entrance lobby was not completely restored, but partially: the pavilions themselves were restored, and the fountain and staircase were reconstructed.


25. Now the first two segments have been assembled and are slowly moving to their place on the south stand. But due to the fact that the bridge was completed there recently, now we have to wait until the guide rails are installed, along which the segments move.

26. Some kind of grandiose kingdom of truss structures and metal.


27. On the slipway, the segments are assembled with the highest precision. Next, they are prepared for transportation, where they are joined with already completed and installed roof segments. Essentially, it will be a bagel. And in the center there is a sliding roof segment.


28. Without reading below, try to guess how the segments slide along the guides?


29. Close-up of the pylon. His negative angle of work raised many questions. It would be more logical to make it positive, that is, it would then look outward. But modern methods of calculation and modeling make it possible to implement very bold projects.


30. Initially, the roof rested only on these pylons, but in the end they came to the conclusion that this was too risky and decided to transfer part of the load to the stadium bowl.


31. Cardan, which transmits forces from the cables to the segment. The fact is that the segment moves along a curve, and the force from the jack is applied only straight.


32. To install the roof, two “rail” tracks were built.


33. Jack. Surprisingly very modest.


34. It was decided to build the Novokrestovskaya metro station on the Nevsko-Vasileostrovskaya line, which by 2017-2018 will become an intermediate station between the Primorskaya and Ulitsa Savushkina stations. They say that work will begin this year.


35. And here is the answer about friction. Sliding is provided by fluoroplastic sheets.


36. Just add a new one and the structure weighing from 621 to 1113 tons glides like butter.


37. The beauty of joints and bolts.


38. Construction of the Western High-Speed ​​Diameter. By the way, there will be parking around the stadium with only 4,000 spaces. With a stadium capacity of 68,000 seats, this means everyone will have to travel by public transport.


39. And several renderings of the stadium. Look how beautiful it will be.


40.


41.


42. Finally, a little story about the name. The fact is that the stadium does not have an official name. It has yet to be approved by the Toponymic Commission. And the name “Zenit Arena” stuck with the light hand of the builders.

1 comment

News from the future 2016
School damaged by Zenit stadium

Roman Moon is about where St. Petersburg children will not go next year.

In August, the government of St. Petersburg announced that 2.2 billion rubles from the 2016 targeted investment program would be redistributed for the completion of the stadium on Krestovsky Island. The list of affected facilities is published on the government website.

505 million of the total amount was initially supposed to go to the construction of schools. One of them is a school in Novaya Okhta, a recent microdistrict beyond the Ring Road of St. Petersburg, the first houses in which were put into operation in 2014. In November 2015, a resident of the microdistrict, Olga Rakhnel, already complained to The Village that there were problems with infrastructure in Novaya Okhta. “The city promises to build the first kindergarten and primary school by the end of 2016, but it’s hard to believe, since construction hasn’t even started,” she said. – Yes, and what they promise is for 300 places, and now more than 2 thousand children are already in need of kindergartens and schools in the first place - we ourselves interviewed people and made lists. And people are about to move in in the second line. The rest - schools, kindergartens, a clinic - are promised after 2018, but the exact dates are not given.”

A separate school should also be built, but this construction has a complicated history. It took three months to find a contractor; the tender results were canceled twice. The first competition was declared invalid due to claims from the antimonopoly service. The second competition was canceled when the customer believed that the participants had filled out the applications incorrectly. The third time, the government order went to ETS. “There was a fierce struggle for the contract, since the contractor will receive almost 1 billion rubles for the work, and in a crisis, such a large government order looks very attractive,” Delovoy Peterburg explained in March. “The winning ETS, according to the terms of the competition, will build a three-story secondary school for 825 places with two swimming pools, two gyms, workshops, and an elevator.”

A resident of Novaya Okhta, mother of three children, Natalya Zykova, says that she received housing here under a program for a large family: “When they provide housing, they do not discuss schools or clinics. They give you an inspection sheet, you go look, if you like it, you sign and take it - or wait further.” She also says that there is a problem with schools in Novaya Okhta.

“The microdistrict is quite large, I’m not the only one here, here we have a lot of social housing and large families with three or more children. My children go to Petrogradka, to their old school, since the nearest schools are schools in the Kalinin district. They don't take us there because of too many classes. We travel for an hour and 20 minutes, using two vehicles. Even in Okhta, it’s very difficult to get on the bus in the morning: everyone goes to kindergarten, school, or work.”

When Natalya Zykova learned from a Fontanka article that the construction of a school for 825 places was being delayed due to the new Zenit stadium, she wrote a petition addressed to Vladimir Putin.

“Construction of the school was supposed to begin in July 2016 and end in December 2017, but the construction company never started construction and pushed the completion date to December 2018. The money earmarked for the construction of a school in the Novaya Okhta residential complex will be transferred to the construction of the stadium. What about our children? The nearest schools in the Kalininsky district do not accept them; there are already too many students there. There are no specialized schools, not even nearby.

We love and are proud of our city and our Country! We hope and believe that our football players will take a worthy part in the 2018 FIFA World Cup! But we don’t want a stadium at the cost of schools and maternity hospitals! We ask the President of the Russian Federation Vladimir Vladimirovich Putin to take the situation of construction of a school in the Novaya Okhta residential complex under personal control and oblige the authorized bodies to begin construction,” reads the text of the petition. Another petition of similar content was submitted by Boris Vishnevsky, deputy of the legislative assembly of St. Petersburg.

Zykova says that the petitions ultimately helped - the construction came to life: “After our petition, jointly signed, Governor Poltavchenko responded to our appeal on TV. Before this, we only had a fence, after which a tractor arrived and active work began. True, they told me that this would all stop at the foundation pit stage, but for now construction is ongoing.”

This is what the construction looked like at the end of last week.

“Today there were about 5 people at the construction site, as they say, there were a little more workers this week, but not much,” Zykova told me last Saturday.

The construction passport states that construction will be completed in 2018. In March of this year, Business Petersburg wrote that construction should be completed before the end of 2017. At the same time, in August, the St. Petersburg Construction Committee told TASS that the redistribution of funds for the construction of the stadium will not affect the timing of the commissioning of social facilities.

A representative of ETS confirmed to Sports.ru that there were indeed problems with financing the construction of the school. The company did not confirm that this is related to construction on Krestovsky Island.

“The fact is that, by order of the construction committee, the budgets for the current year were very seriously reduced,” ETS said. – The schedules were revised accordingly, which was agreed upon by the construction committee. The reason for the delay is the delay in government funding for the new approved limits. I don’t think the reason is the redistribution of money for the stadium. You cannot redistribute money from the school to the stadium. You're an adult, this doesn't happen. This has nothing to do with the stadium."

Zykova also says that in Novaya Okhta there is a problem with kindergartens.

“A kindergarten school was built here, which was also supposed to be completed in the middle of this year. We recruited three classes of first-graders, but it didn’t open on September 1st because there were cranes all around and people were building houses. For safety reasons, they can’t let children in there.”

“RONO promises a launch in January. But this is how the crane stands now; they won’t be able to build a lot of floors before January.”

The government of St. Petersburg emphasized that the redistribution of funds is a completely legal procedure.

“I assumed that when a new contractor came, he would ask for additional funds for the construction of Krestovsky. And so it happened. There is nothing illegal about this. The government has the right to redistribute 10% of funds within the framework of legislation. Understand, nosebleeds need to be built (stadium - author's note) before December. Otherwise, the city of St. Petersburg will suffer a reputational blow. It would be a real shame. Of course, it’s a shame for schools and kindergartens, but, as I have already said several times, everything is happening within the framework of the law,” Vadim Tyulpanov, head of the temporary commission of the Federation Council for preparations for the World Cup, commented on the situation.

“I would like to note that this is the third budget adjustment this year, and there has never been such hysteria. Apparently, everything connected with the stadium causes such a stir,” said Sergei Morozov, chairman of the construction committee.

  • 18 October 2016, 16:26
  • +1 Only registered and authorized users can leave comments.

Krestovsky Island live in real time. Live webcams: Krestovsky Island online, 24 hours a day, without registration, and nearby: Staraya Derevnya, New Derevnya, Chernaya Rechka, Petrogradka, Vasilyevsky Island, Komendantsky Airfield, St. Petersburg. Krestovsky Island is located near: Krestovsky Island (metro station), Divo Island, Krestovsky Island (St. Petersburg), Dynamo (stadium, St. Petersburg).

Nearby webcams

Fight club webcam “K.O. FIGHT", St. Petersburg

The live webcam is installed in the fight club “K.O. FIGHT", St. Petersburg. The camera allows you to observe the professional training of athletes in real time. Club address: St. Petersburg, Vasileostrovsky district, Nalichnaya street, 36k5.
Camera format: 480p video
3.2 km.

WHSD webcam in St. Petersburg: exit to Bogatyrsky Avenue

The WHSD online webcam broadcasts the exit to Bogatyrsky Prospekt and Planernaya Street from the Western High-Speed ​​Diameter in St. Petersburg in real time. The camera is located on the northern section of the WHSD at the toll point on the side of Primorsky Avenue in St. Petersburg (the direction of traffic in the north direction).
Camera format: 720p video
3.6 km.

WHSD webcam in St. Petersburg: entrance from Bogatyrsky Prospekt

The WHSD live webcam in St. Petersburg demonstrates the entrance from Bogatyrsky Prospekt to the Western High-Speed ​​Diameter in real time. The camera is located on the northern section of the WHSD at the toll point towards Primorsky Prospekt of St. Petersburg and the St. Petersburg Arena stadium (the direction of traffic in the southern direction).
Camera format: 720p video
3.6 km.

Live webcam at the intersection of Gakkelevskaya and Kamyshovaya streets in St. Petersburg

The live webcam broadcasts the busy intersection of Gakkelevskaya and Kamyshovaya streets in St. Petersburg. The camera allows you to assess the congestion of the intersection and adjacent roads in real time.
Camera format: 480p video
3.8 km.

Webcam on Commandant Square, St. Petersburg

The online webcam on Komendantskaya Square in St. Petersburg broadcasts in real time the traffic situation at a busy intersection in the Primorsky district of the city. The camera is placed on house number 8 on Komendantskaya Square and is aimed at the intersection of Gakkelevskaya Street and Ilyushina Street, towards the Atmosphere shopping and entertainment complex.
Camera format: 720p video
3.9 km.

Webcam on the spire of Peter and Paul Fortress

The live webcam is located on the spire of the Peter and Paul Fortress (Petropavlovka) on Hare Island in St. Petersburg. The camera shows a view of Vasilyevsky Island in real time.
Camera format: 480p video
4 km.

Overview webcam at the Peter and Paul Fortress

The overview webcam shows the view from the Peter and Paul Fortress in St. Petersburg. The picture from the webcam shows the current air temperature in St. Petersburg.
Camera format: 360p video
4 km.

Webcam in Pevchensky lane, building 5, St. Petersburg

Live street surveillance webcam shows Pevchensky Lane, 5, in St. Petersburg in real time. The camera is placed near the entrance to the 3rd front door of the house. The live online broadcast clearly shows people entering the front door, the sidewalk and part of the roadway of Pevchensky Lane.
Camera format: 480p video
4.1 km.

Wide-angle overview webcam on Petropavlovka

Wide-angle PTZ webcam at the Peter and Paul Fortress in St. Petersburg.
Camera format: 480p video
4.2 km.

Webcams, which broadcast in real time for free for everyone, are installed everywhere: on the streets, in hotels, on embankments and beaches, in shops, airports, train stations, etc.

Krestovsky Island is always online with us. Interested in the weather? Watch the webcam and find out what the weather is like there now.


Online webcam site news:

  • 2019 is coming to an end. He brought us all a lot of good things, and we won’t remember the bad things. Let the coming 2020 be successful for you, everything will work out as it should. In the new year, we wish you the fulfillment of your plans and a wonderful solution to difficult situations. We wish everyone health, ease in life and absence of problems. We all believe in miracles, and they surround us. You just need to look a little closer and understand that a miracle has happened. Have a good start and successful continuation in the new year! Have a wonderful New Year holidays! Happy New Year!
  • Our site has a large addition of webcams from Thailand on the island of Koh Samui.
  • Interesting online webcams of Crimea. Cameras from Crimean resorts will help you see with your own eyes how the holiday season is going in Crimea.
  • New CCTV cameras have been added in the city of Kashira, Moscow region.
  • The site has a large replenishment of Russian online webcams. Now we have more than a thousand webcams of the Russian Federation.
  • Round-the-clock broadcasts from the ISS (with sound) have begun. There are beautiful views of the Earth from space from this artificial satellite of our planet, video broadcasts of dockings, and communication with astronauts.